"Operate on Y" scaling bug
Posted: Mon Jun 13, 2016 5:27 pm
I have a line plot with a maximum value of
Maximum = 6.8472736E+8 at X = 0
as provided by Info > List Peak Values
When I attempt to normalize the ordinate by copying and pasting this maximum value into the "Operate on Y" with
Y=y/6.8472736E+8
The resulting plot ordinate has a maximum value of
Maximum = 1E+16 at X = 0 ?
Strangely, if I delete the "+" between the "E" and "8", the ordinate scale to unity as expected.
Version 2.3.5.3
Thanks for listening, --len
Maximum = 6.8472736E+8 at X = 0
as provided by Info > List Peak Values
When I attempt to normalize the ordinate by copying and pasting this maximum value into the "Operate on Y" with
Y=y/6.8472736E+8
The resulting plot ordinate has a maximum value of
Maximum = 1E+16 at X = 0 ?
Strangely, if I delete the "+" between the "E" and "8", the ordinate scale to unity as expected.
Version 2.3.5.3
Thanks for listening, --len